Key figures (free to quote)
| Item | Reference figure |
|---|---|
| Jakarta (Tanjung Priok) standard clearance | 2-4 working days (complete documents, no inspection). |
| Jakarta inspection (yellow line) | 3 working days standard + 7 working days inspection. |
| Jakarta red line | 3 working days standard + 10 working days red-line handling. |
| Semarang (Tanjung Emas) standard clearance | 2-4 working days. |
| Surabaya (Tanjung Perak) standard clearance | 2-4 working days. |
| PIB filing to SPPB release | 1-3 working days. |
| Inspection profile (empirical) | Yellow line about 10-20%, red line about 3-5% (not official; varies by year and category). |
| PPN (VAT) | Statutory 12%; computed on an 11/12 base, so about 11% effective for non-luxury goods. |
Reference values for standard cases (complete documents, no inspection, outside the red-line season). Actual figures follow current carrier and customs notices. Last reviewed 2026-09-27.
In short
- Out-of-gauge cargo cannot follow general-cargo logic for loading, lifting or transport. Box type, lifting, road leg and quotation all have to be planned per project — general-cargo experience does not transfer.
- The three options carry no ranking, only fit: open top, flat rack and breakbulk are chosen on the cargo’s three dimensions, weight, lifting points and delivery date.
- The biggest cost driver is improvisation. A lift that cannot be made or a road route that cannot be crossed, discovered on arrival, is a very large bill. That is why the weight of this page sits before shipment.
1. What counts as out-of-gauge: the dimensions
- Over height: the cargo sits above the top rail of the box, or exceeds the working height limit once lifted. An open top solves part of the over-height problem by top loading, but there are still stowage limits on what may protrude.
- Over width: the cargo is wider than the internal width, so the adjacent slot cannot be occupied normally. An over-width unit may take up the neighbouring slot on board and be charged on that basis.
- Over length: the cargo is longer than the box, or still overhangs after stowage. The overhanging portion also raises slot-occupancy and lifting-gear questions.
- Over weight: a single piece exceeds the capacity of ordinary lifting gear or of the box. For heavy cargo the key parameters are the weight of the individual piece and the position of the lifting points, not the total weight.
- The yardstick is each port’s and carrier’s operating capability. Limits differ by port and by carrier, and must be confirmed shipment by shipment; whether special arrangements are needed follows the current capability at the load port and the destination port.
2. Which option suits which cargo
Suggested order of preference: where an open top will do, do not use a flat rack (better protection, relatively lower cost); where a flat rack will do, do not go to breakbulk (schedules and pricing are more controllable). But every one of these depends on the dimensions and weight being truthful and accurate — under-declare them and the cost of not fitting is far greater than the cost of changing the plan.
| Option | Suits | Advantage | Cost & caution |
|---|---|---|---|
| Open top | Over-height equipment that is not too wide and can be lifted in from the top | The open top allows top loading and the box walls still give good protection | The soft tarpaulin gives limited rain protection; it does not solve over-width |
| Flat rack | Over-width, over-length and irregular pieces needing side loading | Loose in all three dimensions; the cargo may overhang the box left and right | The cargo is directly exposed, so lashing requirements are high; charged on slot occupancy |
| Breakbulk | Project cargo where a single piece is so large or heavy that no container option fits | Not limited by a box; a heavy-lift vessel handles it directly | Quoted per project, schedules are irregular, fully custom throughout |
3. Extra arrangements: port lifting and the road leg
- Confirm the capability at both ends: what the load port can lift on must also be liftable off at the destination. Lifting-gear tonnage and working methods differ from port to port in Indonesia, so the destination discharge capability has to be confirmed before booking — not improvised once the cargo arrives.
- Lashing and dunnage: flat-rack cargo is directly exposed to the marine environment, and the lashing plan follows the carrier’s requirements. For significant projects, have a professional lashing team do the work and keep photographic records.
- The road leg: over-gauge pieces involve trailer selection, escorting and routes with height, weight and bridge limits. In Indonesia the arrangement is determined by local trailer resources — survey the last-mile route in advance; see the trucking cost page.
- Time characteristics: from enquiry to plan to booking to execution, the cycle is far longer than for general cargo. Schedule it as a project, leaving approval and confirmation time for every stage.
- Insurance: high-value, multi-handling cargo requires reading the cover and the deductible clause line by line; see the cargo insurance page.
4. Cost and time characteristics (wide ranges)
| Item | Characteristic | Note |
|---|---|---|
| Freight | Significantly higher than general cargo of the same weight | Charged on occupied slots or quoted per project; current quotation prevails |
| Slot occupancy | The portion outside the box is charged as adjacent slots | How much over-width or over-length is confirmed with the carrier against the stowage plan |
| Lifting charges | Incurred once at each end | Charged on tonnage and difficulty; confirm port by port |
| Lashing and securing | Professional lashing priced on the plan | Essential for heavy pieces; do not cut it |
| Road leg | Trailer and escort priced per project | In Indonesia, over-gauge transport is priced on the actual route |
| Cycle time | Weeks and up, set by the project | Plan confirmation, booking approval and scheduling both ends all take time |
5. Pre-shipment checklist
- The three parameters: length, width and height; the weight of each piece; and the centre of gravity plus lifting-point positions. Work from the drawings, do not estimate. These parameters are the input to everything else — get one wrong and the whole plan is redone.
- Capability at both ends: the load-port lifting plan and the destination discharge capability, confirmed in writing before booking.
- Box type and slot occupancy: confirm with the carrier which box type is used, how many slots are occupied, and on what basis it is charged.
- The last-mile route: height, weight and bridge limits on the route from the destination port to the site or factory, surveyed and confirmed by the local trailer operator.
- Documents and declaration: the goods description follows the classification position (the method is on the machinery classification page); for categories under control, confirm the qualification requirements in advance.
Oversize by air: the constraint is the cabin door, not the weight. For very large pieces moved by air freight the limit is not weight but size — the door opening, the pallet build-up and the aircraft type together decide whether it can be loaded at all. See air freight to the islands for the flyable dimensions and weights.
Related pages
This page summarizes field practice and publicly available Indonesian import rules for general business reference only—it is not legal, customs, or pricing advice. Customs provisions, tariff rates, and licensing requirements keep changing, so the rules in force at the time and the official processing result always prevail. Wuhan Freedom International Logistics Co., Ltd. · Licensed PPJK in Indonesia · Jakarta / Semarang / Wuhan.