Key figures (free to quote)
| Item | Reference figure |
|---|---|
| Jakarta (Tanjung Priok) standard clearance | 2-4 working days (complete documents, no inspection). |
| Jakarta inspection (yellow line) | 3 working days standard + 7 working days inspection. |
| Jakarta red line | 3 working days standard + 10 working days red-line handling. |
| PPh 22 (without API) | 7.5% (uplifted a further 100% where no tax ID is held). |
| Import duty (BM) | Commonly 0-15% (set by HS code; with FORM E under ACFTA, most goods can reach 0%). |
| De minimis threshold | Goods valued below USD 3 are exempt from duty (PPN still applies). |
| NIB / API processing | NIB 1-2 working days; import licence (API) 3-7 working days. |
| LS survey (Laporan Surveyor) | 3-7 working days (including issuance). |
| FORM E issuance | 1-3 working days (issued by Chinese customs / CCPIT). |
Reference values for standard cases (complete documents, no inspection, outside the red-line season). Actual figures follow current carrier and customs notices. Last reviewed 2026-09-27.
In short
- Booking lead time is not one number; it is a table split by container type and season. General dry boxes, special equipment and dangerous goods rest on entirely different space logic. Applying a single “book a week ahead” will certainly fail in peak season.
- Booking too late does not mean “a few days later”. It means a rolled booking, a changed sailing, a missed preferential-certificate window and free time eaten at the destination — a whole chain moving together.
- This page gives ranges rather than fixed figures. Ranges move with the market; the carrier’s space confirmation at the moment of booking is what governs.
1. What happens when lead time is too short: one chain
What lead time actually buys. Not the appearance of being organised, but three things: the ability to choose this week’s sailing, room to re-date after a problem, and time to re-sequence the document chain. All three exist only when there is a surplus.
- Step one — you cannot get on the intended sailing. Space is full, or equipment is short, and the cargo rolls to the next voyage. In peak season “the next voyage” can mean a week or considerably more.
- Step two — the document chain falls out of step. The certificate of origin, invoice dates and declaration rhythm were all scheduled against the original sailing; change the ship and the documents must be re-sequenced. If a preferential certificate has already been issued and the sailing moves a long way, the consistency between the certificate and the transport information comes into question.
- Step three — the destination-side window is squeezed. With arrival pushed back, the clearance and delivery slots already arranged must be re-booked, free container and storage time starts on schedule regardless, and the risk of overrun charges rises directly.
- Step four — contract delivery risk. Any of the above accumulating ends as a missed delivery date. That is why lead time is worth spending money to protect.
2. Indicative ranges by container type (general approach)
| Box type / cargo | Typical lead time, off-peak | Typical lead time, peak | Note |
|---|---|---|---|
| General dry container (FCL) | A few days to a week | One to two weeks, longer when very tight | Governed by the space confirmation at booking |
| LCL | A few days | More than a week | Also requires time for consolidation and box allocation |
| Open-top / flat-rack and other special equipment | One to two weeks | Two to three weeks or more | Equipment repositioning is costly; if no unit is in port you wait for one |
| Reefer | One to two weeks | Two to three weeks | Confirm plugging and pre-trip temperature inspection arrangements |
| Dangerous goods | Two to three weeks or more | Earlier still, confirmed sailing by sailing | Carrier approves each booking individually; not every ship carries them |
| Out-of-gauge / heavy lift | Scheduled per project | Scheduled per project | Involves lifting plans and road permits |
The ranges are a general approach to the problem; the carrier’s space position and acceptance criteria at the time of booking govern in practice.
3. Season, and the holiday windows
- Before Chinese New Year: factories rush cargo out before shutting down, so space and trucking tighten at the same time — one of the tightest windows of the year. Take the peak-season figure and add.
- Ramadan and Idul Fitri in Indonesia: terminal working rhythm and clearance efficiency are both affected, and stock-building before the holiday adds pressure from the other side. See the red-light season page for the pattern.
- The normal peak: the traditional second-half shipping high, with space and freight rising together. Here the order is “lock the space first, complete the instructions later”, not waiting for the paperwork to be complete before booking.
- Off-peak: space is loose, but carriers may merge or trim sailings, and falling sailing frequency can cancel out the advantage of easy booking. Checking the schedule matters more, not less — see the vessel schedule page.
4. Why special equipment and dangerous goods go earlier
- Equipment is scarce. Open-tops, flat-racks and reefers are far less evenly distributed than general dry boxes; if there is no unit at the port of loading, one has to be repositioned, and that time is not yours to control.
- Approval is per shipment. Dangerous goods space requires the carrier to approve each booking against the cargo documentation; incomplete paperwork never enters the queue, and the approval cycle stacks on top of the equipment cycle, so lead time roughly doubles. See the dangerous goods booking page.
- Stowage is restricted. The positions a ship can allocate to special equipment and dangerous goods are limited, and each ship can take only so many — first come, first served.
- The cost of recovery is high. Rolling a general box to the next sailing is an inconvenience; rolling special equipment can mean waiting for the next voyage that has a unit available, at an interval nobody can predict.
5. Back-scheduling worked example: from contract date to latest booking day
- Assumption (illustrative values, reproducible): the contract delivery date (cargo in the customer’s warehouse) is 20 November. Working backwards: last-mile delivery 1–2 days → clearance and release 2–5 days (complete documents, no inspection) → sea voyage including transshipment 8–15 days (depending on direct call or transshipment) → 2 days for cut-off and instructions → 3–7 days of buffer between booking and sailing.
- Total: roughly 16–31 days in the smooth case. Taking the conservative end, the latest sailing date should be early November, and the latest booking day one lead-time notch before that; peak season, special equipment and dangerous goods each move it further forward using the table in section 2.
- Cross-check: set the back-scheduled result against the certificate issuing cycle and the factory’s cargo-ready date. The plan only holds if all three timelines can be satisfied at once. If any one cannot, adjust the shipping plan rather than betting that a step can be compressed.
- The clearance timeline after arrival is set out on the clearance lead time page; the preparation checklist before arrival is on the clearance documents page.
Related pages
This page summarizes field practice and publicly available Indonesian import rules for general business reference only—it is not legal, customs, or pricing advice. Customs provisions, tariff rates, and licensing requirements keep changing, so the rules in force at the time and the official processing result always prevail. Wuhan Freedom International Logistics Co., Ltd. · Licensed PPJK in Indonesia · Jakarta / Semarang / Wuhan.