Key figures (free to quote)
| Item | Reference figure |
|---|---|
| Free time (detention free days) | 7 days from discharge by default (extension to 14 days can be requested). |
| Demurrage 20GP | IDR 400,000–1,050,000 per day after free time (escalating bands, ≈USD 22–58). |
| Demurrage 40HQ | IDR 700,000–1,575,000 per day after free time (escalating bands, ≈USD 39–88). |
| De minimis threshold | Consignments under USD 3 are duty-free (PPN still applies). |
| NIB / API processing | NIB 1-2 working days; API import licence 3-7 working days. |
| LS survey (Laporan Surveyor) | 3-7 working days including certificate issuance. |
| FORM E issuance | 1-3 working days (issued by China Customs / CCPIT). |
| Jakarta city delivery | 1-3 days after customs release. |
| Java island delivery | 2-4 days. |
Reference values for standard cases (complete documents, no inspection, outside the red-line season). Actual figures follow current carrier and customs notices. Last reviewed 2026-09-27.
In short
- Demurrage — the container sits inside the terminal past free time. Detention — the container is out but not returned. Storage — the cargo itself sits, in terminal or CFS.
- Each clock has its own free time, starts on its own trigger, and bills per day — often on rising day-bands.
- They are not alternatives: one stuck container can run two or three clocks at once.
- The cure is always the same and always upstream: documents ready, funds ready, D/O collected fast. See Customs Clearance Service.
The three clocks, separated
Importers who conflate these three cannot forecast them. The table is the mental model; actual free time and rates vary by carrier and terminal and are subject to the prevailing tariff.
- FCL cargo normally faces demurrage + detention; LCL cargo faces storage at the CFS while the consolidation is deconsolidated and cleared.
- Free time is negotiated per line and port — confirm yours in the quote, never assume it.
| Charge | Applies to | Clock starts | Billed by |
|---|---|---|---|
| Demurrage | The container, inside the port | When free time ends after discharge | Per day, usually in rising day-bands |
| Detention | The container, outside the port | When the container leaves the terminal, until empty return | Per day, often flat then escalating |
| Storage | The cargo | Cargo at terminal or CFS past free storage days | Per day (per CBM at CFS for LCL) |
What each clock is actually incentivizing
The charges are not punishment; they are pricing a scarce resource — terminal space and container fleet circulation.
- Demurrage pushes you to clear and pull the box out so the terminal slot can be reused.
- Detention pushes you to return the box so the carrier can reload it elsewhere.
- Storage pushes documents to move while goods wait, not the reverse.
- All three therefore reward exactly one behavior: preparing the import file before the vessel arrives.
A day-by-day accumulation example
Illustrative example: one 40HC discharged in Jakarta, 5 free demurrage days, 5 free detention days; an LCL alternative is shown in the note. Rates are illustrative and vary by carrier — subject to the prevailing tariff.
| Day after discharge | Demurrage (day-band, illustrative) | Cumulative demurrage | Detention if picked up late (illustrative) |
|---|---|---|---|
| 1–5 | Free time | 0 | Free if returned within 5 days of pickup |
| 6 | 50 | 50 | 60/day begins |
| 8 | 50/day | 150 | 180 (3 days) |
| 10 | 50/day ends band | 250 | 300 (5 days) |
| 11 | 75/day band begins | 325 | 360 (6 days) |
| 12 | 75/day | 400 | 420 (7 days) |
| 15 | 75/day band ends | 625 | 600 (10 days) |
| 16+ | 100/day | keeps climbing | keeps climbing |
Same story, LCL version: A 6 CBM LCL lot at the CFS with 3 free storage days and an illustrative USD 3/CBM/day afterwards: cleared on day 10 means 7 billable days × 6 CBM × 3 = USD 126 — plus the CFS handling you were always going to pay. Small boxes bleed slower, but they bleed.
Reading the example correctly
Three observations that generalize to every real bill.
- Bands accelerate. Day 12 costs more than day 6 not by a little but structurally — the day 11–15 band is 50% above the first band in the example.
- Clocks overlap. If the container is picked up on day 12 and returned on day 19, detention runs those 7 days while demurrage stopped at pickup — but if pickup was late, demurrage already billed days 6–12.
- Storage can ride on top when cargo is moved to a warehouse or bonded store pending documents — a third invoice for the same waiting time. See Warehousing Options.
The prevention stack
Every long demurrage bill we have seen reduces to one of five upstream failures. All five are fixable before sailing.
- Documents incomplete at sailing — invoice, packing list, B/L consistency checked pre-departure. See Documents Checklist.
- Permits not applied for — Lartas cargo needs the licence before the goods. See Lartas & Restricted Goods.
- FORM E problems — certificate issues take days to fix that you do not have after arrival. See FORM E & ACFTA.
- Duty funds not ready — the payment channel will not release on an IOU.
- D/O handled slowly — the step between release and pickup; direct handling buys back free days. See Choosing a Forwarder.
If the clock is already running
When cargo is already sitting past free time, sequence matters more than effort.
- Fix the binding constraint first — usually the missing permit or document, not the payment.
- Ask the terminal about free-time extension requests — sometimes granted with cause, sometimes cheaper than the alternative.
- If the box cannot be cleared soon, moving cargo to a bonded store can stop the worst clock — compare rates before moving. See Warehousing Options.
- Track the running total daily so decisions are made on numbers, not anxiety. See Detained Cargo Costs.
Demurrage fee, detention charge, storage: one event, three invoices
Importers searching for demurrage fees, detention charges and storage costs are usually looking at the same physical problem — a container that outlived its free time — while the invoice in front of them carries only one of the three names. Getting the name right decides who you are actually arguing with.
| Label on the invoice | What it is | Who bills it | Clock starts |
|---|---|---|---|
| Demurrage / demurrage fee / demurrage charges | The container sitting inside the terminal | The carrier, or the terminal under the carrier's tariff | Discharge date, for import boxes |
| Detention / detention fee / detention charges | The container taken out of the terminal and not yet returned empty | The carrier | Gate-out, and stops on empty return |
| Storage / port storage | Terminal or port space rented by the cargo | The terminal or port operator — a separate bill from the carrier's | After the port's own free period |
| Free time / free days / free period | The allowance before any of the above starts, sometimes quoted as combined D&D | Granted by the carrier, confirmed in writing | Counted from the events above, in calendar days |
Three consequences follow, and each one is worth money:
- Do not appeal a detention charge to the terminal. Demurrage and detention are released by the carrier, storage is released by the terminal. Sending the request to the wrong desk is the most common way a dispute loses a week.
- Check which clock the days are counted from. A demurrage invoice counted from discharge and a detention invoice counted from gate-out can describe the same fortnight and still be two legitimate bills.
- Check whether the charge has already been settled. Detention is frequently collected at gate-in of the empty box, so what arrives later may be a statement rather than a new claim.
For the size of the numbers, our lane pages carry the indicative bands for Jakarta and Semarang — for instance Ningbo to Jakarta and Qingdao to Semarang. The starting events themselves are set out in free time and D/O release, the day-by-day accumulation is the example above, and what the same delay does to the rest of the file is in detained cargo costs.
Related pages
This page summarizes field practice and publicly available Indonesian import rules for general business reference only—it is not legal, customs, or pricing advice. Customs provisions, tariff rates, and licensing requirements keep changing, so the rules in force at the time and the official processing result always prevail. PT SHOULDER International Logistics · Licensed PPJK in Indonesia · Jakarta / Semarang · China side: Wuhan Freedom International Logistics Co., Ltd..
Frequently asked questions
What is the difference between demurrage, detention and storage?
Demurrage bills the container inside the port past free time; detention bills the container after pickup until empty return; storage bills the cargo itself at the terminal or CFS. They are separate clocks with separate free time and can run simultaneously.
How many free days do I get at Indonesian ports?
It varies by carrier, terminal and even contract — commonly a handful of days for demurrage and a similar window for detention. Confirm the exact free time in your quotation and booking confirmation; never assume.
How fast do these charges grow?
Usually in rising day-bands: the days 6–10 rate, then a higher band, then higher still. The worked example shows a typical escalation shape — the 16th day costs roughly double the 6th day in that illustration.
Can demurrage be waived?
Sometimes, with cause and documentation, via a request to the carrier or terminal — for example systemic congestion. But waiver is a favor, not a right, and it is never a plan. Preparation is the only reliable avoidance.
Do LCL shipments pay demurrage?
LCL pays CFS storage rather than container demurrage — the cargo is at the CFS from deconsolidation, usually with a few free days, then billed per CBM per day. The clock and the pricing basis are different but the discipline is identical.
Who pays these charges if I bought DDP?
Under genuine DDP the seller side carries them — but only a genuinely structured DDP, with a real importer of record. If your "DDP" is an undername arrangement, read the contract and then the undername risks page.
What is the single best prevention?
Have the complete import file ready before the vessel sails: verified HS, permits in hand, FORM E valid, tax IDs correct, and duty funds staged. Clearance then finishes inside free time as a matter of routine.
Can I move my cargo out of the port to stop the charges?
After release, yes — trucking the cargo out stops demurrage and starts detention on the box. Before release, options like bonded storage may exist case by case. Compare the daily rates before moving anything.
Key questions on this page, free to quote.
What is the difference between demurrage and detention?
Demurrage is time the container spends inside the terminal after discharge; detention is time it spends outside the terminal after collection, until the empty box is returned. They are separate clocks under one carrier tariff, and both run in calendar days.
Are detention fees and detention charges the same thing?
Yes. The two phrases describe the same carrier charge, and demurrage fee and demurrage charges work the same way. What decides the dispute is which clock the invoice is counted from, not the wording on it.
When does detention start on an import container?
Normally at gate-out, when the box leaves the terminal, and it ends when the empty container is returned. Demurrage on the same box starts earlier, on the discharge date. Free time and D/O release explains how the free days attach to each event.
Official sources
Independently verifiable channels below. Rates, restrictions and lead times follow each agency's latest publication.
- Directorate General of Customs and Excise (Bea Cukai) — Clearance process, PIB filing and customs rules
- Indonesia National Single Window (INSW) — Unified platform for Indonesia import/export filing, licensing and documents
- World Customs Organization (WCO) — International HS code and classification rules