Key figures (free to quote)
| Item | Reference figure |
|---|---|
| Jakarta (Tanjung Priok) standard clearance | 2-4 working days (complete documents, no inspection). |
| Jakarta inspection (yellow line) | 3 working days standard + 7 working days inspection. |
| Jakarta red line | 3 working days standard + 10 working days red-line handling. |
| Outer island delivery | 5-10 days including onward transfer. |
| Semarang (Tanjung Emas) standard clearance | 2-4 working days. |
| Surabaya (Tanjung Perak) standard clearance | 2-4 working days. |
| PIB filing to SPPB release | 1-3 working days. |
| Inspection rate (practical range) | Yellow line approx. 10-20%, red line approx. 3-5% (not official statistics; varies by season and commodity). |
| PPN (VAT) | Effective 11% (statutory 12%; non-luxury goods taxed on an 11/12 base). |
Reference values for standard cases (complete documents, no inspection, outside the red-line season). Actual figures follow current carrier and customs notices. Last reviewed 2026-09-27.
Classify by function, not by name
Indonesian classification follows the BTKI / HS logic, where a machine’s tariff line follows its function and design, not its marketing name. A "packaging machine", a "food machine" and a "multi-purpose industrial robot" can sit in different chapters with different duty and Lartas outcomes.
- Describe the machine by what it does, the material it processes, and whether it is designed for a specific industry — that trio usually pins the heading.
- Multi-function machines follow the principal-function logic; when genuinely ambiguous, the PPJK’s reasoned classification and, if needed, a formal ruling beat guesswork.
- We cross-check every line on INSW / BTKI before the container sails. See HS Classification Guide.
Spare parts vs complete machine
The single most common machinery dispute: is this a machine, or a part of one?
| Shipment reality | Classification direction | Practical consequence |
|---|---|---|
| Complete machine, one crate | Machine heading for its function | Straightforward; normal Lartas screening |
| Machine shipped in modules for one project | Usually the machine heading, with the packing list proving the set | Splitting across HS lines to "save duty" invites queries |
| Genuine spare parts | Part headings, often with their own duty rates | Invoice must show part numbers and machine compatibility |
| Parts that are themselves machines (motors, pumps) | Their own headings | Do not lump under "parts" — value density triggers review |
Costly mistake: Declaring a complete machine as "spare parts" to catch a lower duty line. When physical inspection shows an assembled machine, the reclassification, duty shortfall and delay all land on the importer — and the record follows your NPWP.
Used machinery: extra scrutiny is the norm
Used machines are not automatically blocked, but they face tighter checking: age, condition, remaining service life, and in some lines additional technical requirements under the rules in force.
- Expect questions about manufacture year and condition — have the supplier state both on the invoice.
- Photograph the machine before packing; it both supports the declaration and documents what was actually loaded.
- Budget schedule slack: a used machine is more likely to be flagged for document or physical review than an identical new one.
Wooden packaging and ISPM awareness
Heavy machines almost always travel in solid wood crates or on wooden skids — which makes packaging a compliance item, not just a protection item.
- Solid wood packing material is expected to meet ISPM-type treatment (heat treatment or fumigation) with the IPPC marking stamped on the wood.
- Non-compliant wood can trigger quarantine action on arrival — re-treatment, re-packing, or delay — while demurrage runs.
- Alternatives exist: plywood and plastic do not carry the same solid-wood expectation and often avoid the issue entirely. Specify packaging material in the booking.
Cost and time: a worked duty example
Illustrative numbers only — the duty rate depends on the exact BTKI line and the rules in force, and freight is subject to the prevailing quote. The arithmetic is what you should recompute with your own figures.
- Transit is typically about 9–14 days to Jakarta by sea plus clearance time; a machine that needs a pre-shipment technical review adds lead time on the documents side, not the ocean side.
- For heavy-lift or out-of-gauge machines, lifting and trucking costs change the picture — see Trucking & Last Mile.
| Line item | Basis | Illustrative amount (USD) |
|---|---|---|
| CIF value (goods + freight + insurance) | Invoice + freight + insurance | 30,000 |
| Import duty (BM) at an assumed 5% | 5% × 30,000 | 1,500 |
| Tax base = CIF + BM | 30,000 + 1,500 | 31,500 |
| PPN, ~11% effective (12% statutory on DPP = 11/12 of base) | 31,500 × 12% × 11/12 ≈ 31,500 × 11% | 3,465 |
| PPh 22 at 2.5% (API + NPWP tier) | 2.5% × 31,500 | 787.50 |
| Total duty + taxes | 1,500 + 3,465 + 787.50 | 5,752.50 |
Machinery emergencies: fly the part, ship the machine
A stopped line costs more than the freight, so the usual split is a flown spare part and a sea-shipped machine, sharing one HS and permit preparation. Air size and weight limits for machinery parts are on the Surabaya to outer-island air freight page.
Related pages
This page summarizes field practice and publicly available Indonesian import rules for general business reference only—it is not legal, customs, or pricing advice. Customs provisions, tariff rates, and licensing requirements keep changing, so the rules in force at the time and the official processing result always prevail. PT SHOULDER International Logistics · Licensed PPJK in Indonesia · Jakarta / Semarang · China side: Wuhan Freedom International Logistics Co., Ltd..
Frequently asked questions
How is machinery classified for Indonesian customs?
By function and design under the BTKI/HS system — what the machine does and what it processes decide the heading, not the product name. Ambiguous multi-function machines follow the principal-function logic, and borderline cases can be confirmed through formal channels.
Can I import used machinery into Indonesia?
Often yes, but used machines face extra scrutiny: age, condition and remaining service life are questioned, and some lines carry additional technical requirements. State the manufacture year and condition on the invoice and expect some schedule slack.
Do spare parts and complete machines have the same duty?
Not necessarily — parts often sit in their own headings with different rates. Declaring a complete machine as parts to chase a lower rate is exactly the kind of mismatch that triggers reclassification and delays.
Does wooden packaging need treatment?
Solid wood packing material is expected to meet ISPM-type heat treatment or fumigation with IPPC marking. Non-compliant wood can cause quarantine action on arrival. Plywood and plastic packaging generally avoid the issue.
What taxes apply when importing a machine?
Import duty on CIF value, then PPN and PPh 22 on the base of CIF plus duty. PPN is 12% statutory with a DPP of 11/12 of the base for non-luxury goods (about 11% effective); PPh 22 is 2.5% with API and NPWP under the tiers in force.
Can I split one machine into several HS codes?
A machine shipped complete should be declared as the machine, even if it arrives in modules. Genuine separate spare parts can take their own headings. Splitting one machine across lines to reduce duty is a red flag, not a strategy.
How long does machinery clearance take?
Document-quality dependent. With clean classification and complete permits, release can be quick; with used machines or Lartas lines, allow extra days for document review. Transit itself runs roughly 9–14 days by sea to Jakarta.
Is out-of-gauge machinery handled differently?
Yes — flat racks, open tops, lift-on/lift-off charges and route surveys change both cost and time materially. Flag dimensions and lifting points at quotation stage so the plan, not the port, is where surprises happen.
Key questions on this page, free to quote.
Official sources
Independently verifiable channels below. Rates, restrictions and lead times follow each agency's latest publication.
- Directorate General of Customs and Excise (Bea Cukai) — Clearance process, PIB filing and customs rules
- Indonesia National Single Window (INSW) — Unified platform for Indonesia import/export filing, licensing and documents
- Ministry of Trade (Kemendag) — Import/export licensing, Lartas restrictions and trade rules