Home / Indonesia Import Guide / Waiver Application

Can Demurrage and Detention Charges Be Waived? Conditions, Evidence and How to Apply

Overrun charges are neither impossible to reduce nor reducible on request. A waiver rests on three things: the delay was not your fault, the cause can be shown in writing, and the application is timely and well made. This page sets out which situations leave room, what evidence to assemble, whom to approach and when, how to write the application — and when it is not worth the effort.

Updated 2026-09-22Cost & chargesLicensed PPJK in Indonesia

Key figures (free to quote)

ItemReference figure
Free container days7 days by default, counted from the discharge date; extension to 14 days can be applied for.
Detention, 20GPIDR 400,000-1,050,000 per day (steps up after the free period; roughly USD 22-58).
Detention, 40HQIDR 700,000-1,575,000 per day (steps up after the free period; roughly USD 39-88).
LS survey (Laporan Surveyor)3-7 working days including issuance.
FORM E issuance1-3 working days (issued by China Customs / CCPIT).
Jakarta city deliveryDelivered within 1-3 days of release.
Java island delivery2-4 days.
Outer island delivery5-10 days including the second-leg transhipment.
Free port storage3-5 days.

Reference values for standard cases (complete documents, no inspection, outside the red-line season). Actual figures follow current carrier and customs notices. Last reviewed 2026-09-27.

In short

1. Situations with room to apply

Three situations with no room. Documents not complete, payment delayed, or the address and consignee not cooperating — these fall within the importer’s own responsibility, and a waiver application is essentially futile. Effort is better spent improving the pace next time — see the hidden costs page.

SituationWhy there is roomDirection of evidence
Port or customs system failure, official operational delayThe delay sits in an official channel, not the importer’s faultOfficial notices, system announcements, operational records
Force majeure (weather, port closure, strikes)An industry-wide stoppage; carriers usually have a waiver practiceOfficial suspension notices, weather and port announcements
Carrier-caused (rolled cargo, document error, return depot closed)The carrier’s own faultCarrier emails, timeline records
Inspection occupying the free periodThe cargo is inside an official inspection procedureA comparison of the inspection notice against the release time
Commercial reduction for a long-term customerThe value of the relationship and the credit recordCooperation history and volume data

2. Evidence: the timeline is the core

EvidenceWhat it provesSource
Arrival NoticeThe baseline date from which the free period runsCarrier / carrier’s agent
SPPB release timeWhen the customs stage was completedDeclaration system / PPJK
Collection booking and operational recordsWhether the container was collected promptly after releasePort authority / trucking company
Third-party proof of the cause of delayThat the delay sat in an official or carrier channelAnnouncements, emails, notices
Container return receiptThe actual time of returnDepot

3. Whom to approach, and when

4. A worked example: how to cost the application

ItemBasisResult
Period within your controlD0-D5 (documents and payment completed on plan)5 days, no responsibility
Delayed periodD5-D10 port system failure (official notice available)5 days, the claimed interval
Normal collection and return periodD10 collection → D12 return (2 days)Within the remaining free entitlement
Amount claimed5 days overrun × the applicable rate; seeking a full waiver for the system-failure periodRecomputed by substituting the rate

Assumed conditions (illustrative): 7 free container days (on- and off-terminal combined), D0 arrival; a port system failure delays the SPPB until D10, collection at D10, return at D12. Actual occupation 12 days, overrun 5 days.

5. Reducing the need to apply at all

Ask about this shipment Estimate duty & delivery Check HS code & Lartas

Related pages

Demurrage, Detention & StorageWarehousing & StorageHidden CostsCustoms DetentionClearance Lead TimeIndonesia Import Guide

This page summarizes field practice and publicly available Indonesian import rules for general business reference only—it is not legal, customs, or pricing advice. Customs provisions, tariff rates, and licensing requirements keep changing, so the rules in force at the time and the official processing result always prevail. Wuhan Freedom International Logistics Co., Ltd. · Licensed PPJK in Indonesia · Jakarta / Semarang / Wuhan.

Frequently asked questions

Can container demurrage and detention charges be waived?

Yes, but with conditions: the cause of the delay was not the importer’s (for example a port failure, force majeure, carrier fault, or an inspection occupying the period), and written evidence plus a complete timeline can be provided. Dwell caused by the importer’s own side — incomplete documents or delayed payment — essentially leaves no room to apply.

Whom should the waiver application go to?

To the party to whom the charge belongs: on-terminal and off-terminal detention go to the carrier, and port storage goes to the terminal or depot. Approaching the wrong party is a common reason an application fails — first separate the three charges and their owners.

When is the best time to apply?

As the free period is running out and the overrun is happening, when it is still a warning-stage negotiation and the carrier has room to schedule. Once the invoice is out it becomes a post-hoc haggle. Either way, submit in writing with the evidence attached.

What evidence does the application need?

One timeline plus its supporting documents: the Arrival Notice, the SPPB release time, the collection booking and operational records, third-party proof of the cause of delay (announcements, emails), and the container return receipt. Split the overrun days into a period within your control and a period of objective delay — the more precise the interval, the more likely it is accepted.

Is a partial reduction worth accepting?

Usually yes. The negotiation rests on evidence: bank the interval you can prove, and decide on the remainder according to the value of the ongoing relationship. Even after a partial reduction, ask for written confirmation and settle against the confirmed amount.

Can the free period be paused during an inspection?

Where the cargo cannot be collected because it is inside an official inspection procedure, the container usage charge for that period can be claimed from the carrier against a comparison of the inspection notice and the release time. This is one of the easier cases to establish, because the cause of occupation is clearly in an official channel.

Does a long-term relationship earn a reduction?

It can, as a commercial reduction: a steady volume and a good credit record are themselves negotiating chips. Beyond billing disputes, keep an annual summary of container volume and on-time return records as background material for ongoing communication.

How can overruns be reduced at the source?

Three things: agree the free-time clause before taking the container and write it into the confirmation; bring the declaration schedule forward so release lands inside the free period; and budget time on the least favourable case during peak season. One day saved at the source beats ten waiver applications afterwards.

Official sources